Senate2025-26 session

SSB 6076 — Streamlining consumer-owned utility procurement requirements for clean energy generation, energy storage, transmission, and distribution projects.

Signed into law — Chapter 183, Laws of 2026

Sponsor
Goehner
Introduced
January 30, 2026
Status
C 183 L 26
Last action
Effective date 6/11/2026. (March 24, 2026)

What this bill does

Allows a public utility district (PUD) to have its own personnel perform work up to $1 million in value through prudent utility management. Allows certain utilities to receive hard copy or electronic bids for public works projects. Allows a PUD to use an alternative purchase contract process and waive competitive bid requirements for certain public works projects.

From the Washington State Legislature's nonpartisan staff bill analysis. Read the full analysis ↗

Floor votes

  • House — Final Passage as Amended by the House · March 4, 2026
    95 yea · 1 nay · 2 not voting
  • Senate — 3rd Reading & Final Passage · February 11, 2026
    48 yea · 1 nay
  • Senate — Final Passage as Amended by the House · March 10, 2026
    48 yea · 1 nay

Track SSB 6076 on OlympiaTrack

A free account adds a plain-English AI summary, the full hearing and amendment record, who testified, and roll calls by member. Plus email alerts when this bill moves.

Create a free account

Other bills sponsored by Goehner

All 2025-26 Washington State bills →

Source: the Washington State Legislature. OlympiaTrack is an independent bill-tracking service and is not affiliated with the Legislature. View on leg.wa.gov ↗